Implementation:
The distributor had to receive 2x6 pieces of 4x240mm2 cables, which needed enough space in the cabinet.
The handover was hindered by events outside our control. One of the manufacturers delivered the switchover with a delay of nearly one week.In the end, we completed the installation 2 days later than planned, but 2 days ahead of the electricity supplier’s deadline. We are pleased that our customer also commented our work positively. Our colleagues deserve great praise for that.