Installation of building automation of EMINEO Private Hospital, Budapest
Name of project:
Installation of building automation of EMINEO Private Hospital, Budapest
Our task was:
to install automation systems for regulating the ventilation of the private hospital’s operating rooms, to maintain the pressure and to regulate the exchange of air, heating, cooling, humidification and drying.
We had to implement a system containing 214 data points.
Implementation:
The automatization, cold and hot water supply as well as cooling and heating control of the substation was carried out using 2 pcs of SIEMENS PXC100-E.D DDC and SIEMENS PXG3.W100-1 building monitoring equipment.